Question 1
The piping schedule for a facility operating under EPA's 2021 Multi-Sector General Permit (MSGP) lists four non-stormwater lines proposed for connection to storm drainage. No separate wastewater permit authorizes these flows. Which line carries an allowable non-stormwater discharge, provided the applicable MSGP conditions are met?
Show answer & explanation
Correct answer: D - Uncontaminated condensate from the building's air-conditioning system.